Acceleration Claim

Acceleration Claim

Acceleration Claim

Directed acceleration follows an express instruction to expedite. Constructive acceleration arises where the owner denied a warranted time extension and required completion on the original date, forcing the contractor to compress.

Both require proof of actual added cost.

Alternative Names:

Acceleration|Constructive Acceleration Claim

Why it Matters?

Constructive acceleration requires establishing that an excusable delay occurred, that a timely extension request was denied, and that the owner insisted on the original date, which is a four-element chain where any missing link defeats the claim. Contractors that accelerated without requesting an extension first have no claim regardless of the added cost. Overtime premiums, added crews, and lost productivity are the recoverable components.

Frequently asked questions

What does constructive acceleration require?

What does constructive acceleration require?

An excusable delay, a timely extension request, denial of that request, and owner insistence on the original completion date.

What defeats the claim?

What defeats the claim?

Accelerating without first requesting a time extension, which breaks the required element chain regardless of added cost.