Excusable delays arise from causes neither party controls, including unusual weather, labor disputes, and acts of government. The contractor receives additional time but not necessarily compensation.
Compensable delays are a subset caused by the owner.
Alternative Names:
Excusable Delay Event|Time Extension Delay
Why it Matters?
Excusable but non-compensable classification is the outcome for most weather and force majeure events, which gives the contractor schedule relief while it absorbs extended overhead. Unusual weather requires comparison to historical norms rather than merely adverse conditions, and contractors are expected to plan for typical seasonal patterns. Documenting weather days against historical averages contemporaneously supports the extension request.
Frequently Confused with
Related terms
Frequently asked questions
Does an excusable delay bring compensation?
What establishes unusual weather?