Delay claims allocate responsibility for schedule impacts. Excusable delays entitle a contractor to time, compensable delays to time and money, and inexcusable delays neither. Concurrent delay complicates the analysis.
Schedule analysis establishes causation.
Alternative Names:
Construction Delay Claim, Schedule Delay Claim
Why it Matters?
Critical path analysis determines whether a delay actually extended completion, since a delay to non-critical work absorbs float without affecting the end date. That distinction eliminates many claims before the entitlement question is reached. No-damages-for-delay clauses further limit recovery to time extensions in jurisdictions enforcing them, though exceptions for active interference and bad faith are widely recognized.
Frequently Confused with
Related terms
Frequently asked questions
What determines whether a delay is compensable?
What limits delay damages?