Concurrent Delay

Concurrent Delay

Concurrent Delay

True concurrency requires that independent delays each affect the critical path during the same period. Where an owner-caused and contractor-caused delay overlap, most approaches grant time but deny compensation.

Apportionment approaches vary.

Alternative Names:

Concurrent Delays, Overlapping Delay

Why it Matters?

The typical resolution grants a time extension while denying delay damages to both parties, which makes concurrency a defense for owners facing compensable delay claims and a defense for contractors facing liquidated damages. That symmetry is why establishing concurrency is frequently the most productive schedule analysis. Proving true concurrency requires showing both delays independently affected the critical path in the same period.

Frequently asked questions

What is the typical outcome of concurrent delay?

What is the typical outcome of concurrent delay?

A time extension without delay damages, which defends owners against compensable delay claims and contractors against liquidated damages.

What does proving concurrency require?

What does proving concurrency require?

Showing that both delays independently affected the critical path during the same period rather than sequentially.