Schedule Analysis

Schedule Analysis

Methods include as-planned versus as-built comparison, impacted as-planned, collapsed as-built, and time impact analysis. Contemporaneous windows analysis using periodic schedule updates is generally regarded as most reliable.

Method selection affects the result substantially.

Alternative Names:

Delay Analysis|Forensic Schedule Analysis

Why it Matters?

Different methods applied to identical facts produce materially different allocations, which is why method selection is contested before the analysis is even examined. Windows analysis using contemporaneous updates is preferred because it reflects what the parties understood at the time rather than a retrospective reconstruction. Absence of schedule updates forces less reliable methods and disadvantages whichever party bears the burden.

Frequently asked questions

Why is method selection contested?

Which method is preferred?