Measured Mile Analysis

Measured Mile Analysis

Measured Mile Analysis

The method identifies a period of undisrupted work as a baseline and compares productivity in disrupted periods. Because both periods involve the same project, crew, and conditions, it controls for variables other methods cannot.

It is regarded as the most reliable productivity method.

Alternative Names:

Measured Mile|Productivity Comparison

Why it Matters?

Baseline selection determines the result, and a comparison period chosen because productivity happened to be high rather than because conditions were genuinely unimpacted invites effective challenge. Establishing that the baseline period was free of disruption using contemporaneous records is the foundation. Where no unimpacted period exists, comparison to similar work on other projects is a weaker fallback that loses the method's principal advantage.

Frequently asked questions

Why is the method preferred?

What determines its credibility?